Sheridan Renewable Energy Project

4 MW Utility Scale — Yamhill, Oregon

Overview

SolRiver acquired Sheridan Solar in the development phase (pre-NTP). The project required management in  engineering, permitting, title work, and equipment procurement.

During construction, Sheridan Solar provided over 60 jobs to the local workforce. 

Sheridan became operational in November 2023. The 4 MW utility-scale project brings clean, affordable energy to over 600 homes in Oregon a year.

0
kWh Energy Produced
July 2023
Construction Begins
November 2023
Operational

Size

4 MW

Solar Modules

6,129

Central Inverter

1

CO2 Avoided

4,563 tons

Technology

Solriver resources for developers
 
  • 6,129 Canadian Solar Modules 
  •  Up to 70 ± 5% bifaciality Factor
  • MBB  cell technology – excellent anti-microcracking performance with more balanced interior stress; grid pattern current path, lower cost

 

  • 1 unit of Sungrow SG3425UD-MV  
  • DC 1500V
  • 600V AC Output
  • Power Factor Rating: >0.99 (+/- 0.8 Adjustable)
  • Array Technology V3
  • Single row, central slew drive balanced system
  • Engineered for long-term durability and reliability
  • Low cost to maintain